In the first days of the new year 2023, line soldiers (DZ) Power Transmission (TTD) Hanoi strengthen supervision work to ensure safety and quality of construction works to increase the load capacity of the 220kV Ha Dong line – Thuong Tin.
The project to increase the load capacity of the 220kV Ha Dong – Thuong Tin transmission line (2-circuit line) is managed by the Power Transmission Project Management Board (NPTPMB), Hanoi Power Center is assigned the task of safety supervision and acceptance of the project. . The project is constructed by Song Hong Electrical Construction Joint Stock Company 4, and PACIFIC Electrical Consulting Joint Stock Company supervises the project.
From January 1, 2023, the first day of the New Year, while the whole country has a Tet holiday to gather with family or rest, construction units, supervision consulting units and operations management units will still diligently executing the project to ensure progress until January 5, 2023 to energize the project.
This is one of the important projects to meet the possibility of long-term future load development, as well as create a solid connection for capacity nodes on the transmission grid in case of normal operation, meeting Supply power when repairing and always ensure safe, continuous power supply to loads in the event of an incident.
Details at: News (ptc1.com.vn)