Scaffolding installation, emergency pull power cord 500kV 3 to National Highway 1A

Monday, 03/06/2024, 13:37 GMT+7

Thanh Hoa – To ensure progress, wherever the pole is erected, the rope will be pulled there. These days, despite the hot weather, contractors and workers are still urgently pulling the 500kV circuit 3 line through National Highway 1A.

As noted by a reporter from Lao Dong Newspaper on the afternoon of June 2, at the construction site of the 500kV circuit 3 line (through Dai Loc commune, Hau Loc district, Thanh Hoa province), workers were still rushing to use equipment, 500kV line traction machine. Photo: Quach Du

It is known that this area is considered a difficult part of the construction, because the road pulls must cross National Highway 1A and the southern railway. Photo: Quach Du

Therefore, before pulling out, the construction contractor, Phuong Hanh Co., Ltd., had to build scaffolding on the national highway, to ensure that the vehicles were still circulating normally. Photo: Quach Du

 

 

The workers in the sun, using the machinery system to pull the wire up. Photo: Quach Du

Proceed to press the anchor lock before placing the wire in the settings. Photo: Quach Du

The electric coils gathered at the construction site. Photo: Quach Du

Workers use the winch system to put the wire in the joints. Photo: Quach Du

On high, officials and workers urgently complete the installation. Photo: Quach Du